Monitor Resource Activity and Operation Execution
You can get a good grasp of the resource workload from the sequence of operations on
each resource. In addition, you can display the execution status of the operations. It
shows which operations are under way, and which operations are complete already, for
example.
-
From the Main View Settings section of the action bar (or Secondary View Settings, if the chart is in the
lower half of the widget window), click Work Order
Color.
-
From the list, select Operation Execution Status.
In the Gantt chart, operations change color to reflect the execution stage they are at.
By default, an operation is:
- Light gray (hex color: #e0e0e0) when the production plan has scheduled it,
but the operation has not reached production yet.
- Dark blue if it is ready for execution; hex color: #005686. The workshop /
teams know they can start working on the operation, but there is no further
information on execution.
- Light blue if it is in progress; hex color: #42a2da. The workshop / teams
have started performing the operation. Execution is under way.
- Orange if it is on hold; hex color: #e87b00. The
workshop / teams have notified they cannot perform the operation, or that
they must stop working on it. If they have given the reason why, it appears
in the tooltip and in the Details panel for the
operation.
- Green if it is complete; hex color: #57b847. The workshop / teams have
finished working on the operation. Execution is complete.
- Dark gray if the execution status of the operation is unknown; hex color:
#77797c. This is an anomaly. You may want to report it
to the persons in charge of the schedule, or of the manufacturing
execution system.
You can choose a different color scheme at any time. If you select Advance / Delay, remember that the
colors on the chart reflect the advance / delay of the work orders, not of
the individual operations. Whatever the color
scheme, specific hatch patterns always identify the operations that are in
progress or complete:
- Black and yellow hatches at the bottom of an operation indicate that the
operation execution is under way. The start date of the operation in the
plan is the date when execution began. The end date is the scheduled end
date.
- A white mesh pattern on an operation identifies the part of the operation
that is complete so far. This goes from the execution start date to the
current date.
- When execution is complete, the white mesh pattern covers the entire
operation bar. The hatches at the bottom disappear. The dates of the
operation in the plan are the start and end dates of its execution.
- In some cases, an operation can appear as both in progress (hatches) and
finished (white mesh on the whole bar). This happens when the app has not
received an execution end date for the operation yet, and the scheduled end
date is before the current date. Because the operation is entirely in the
past, the app considers that it is complete. Yet, until there is an
execution end date to confirm this information, the operation retains its in
progress status.
For clarifications on the current schedule, you can use the highlighting
feature described below to display the links between operations.
Monitor the Schedule of a Work Order on Resources
You can highlight all the operations of a specific work order and see the links between
them. This is useful to find out which resources these operations are using and how they
constrain one another. This can also clarify the reasons for idle times in the schedule
of resources.
-
From the
standard area
of the
action bar,
click
Highlight Work Order.
-
In the bar chart, click an operation of the work order to highlight.
The operation you clicked and those that belong to the same work order appear in color,
with their links. All other operations in the chart are gray. The links show the
order in which the highlighted operations take place, and the dependencies between
them. The links these operations have with operations of other work orders, if any,
appear as well. The colors of the links reflect their type:
- Light green is for precedence links, with or without an
overlap or minimum lead time (delay) between the two operations.
- Cyan is for start-start synchronization links.
- Yellow is for end-start synchronization links.
- Dark red is for end-end synchronization links.
- Dark green is for synchronization links with a maximum
lead time (delay) between the two operations.
- Red is for synchronization links that constrain the two
operations to take place one after the other, using the same resource.
- Dotted lines are for disabled links. Their color
reflects the type of the original link.
Note:
Dashed lines between operations are not process links. They indicate that
the operations are all occurrences of a single operation that is using
several resources at once. If the operation you clicked is one such
operation, it appears in a red frame, with its other occurrences in dashed
red frames, and with dashed red lines between them. Other operations of the
work order that use several resources do not have frames, but they do have
dashed lines between their occurrences. The dashed lines in that case are
the color of the operation.
The number of operations in the work order appears in the search result bar
at the bottom of the chart area. On using the filter feature of the search bar
to drill down the view, see Search and Filters on Gantt Charts.
Note:
If the chart previously highlighted 3DSearch or 6WTags results, it momentarily cancels them so they do not interfere
with the highlighted work order. Similarly, it hides dependency links between work orders. If you are displaying two
charts at a time in the widget, highlighting a work order in one chart
highlights it in the other as well.
To highlight a different work order, click an operation of that work order.
To highlight multiple work orders, Ctrl + click
operations. When you no longer need that feature, click a blank space to
cancel the current selection, and then from the action bar, click the feature icon to disable it. If the chart previously highlighted
3DSearch or 6WTags results, then it highlights them again. This is true also for
dependency links between work orders.
View Details on Resources
You can use the Details panel of the chart to view the
characteristics of resources.
-
On the Resource Gantt Chart, locate the resource to
analyze.
-
If the Details panel is open already, click any
operation on that resource. If the panel is not open, you need to
double-click the operation instead.
Note:
If you are displaying two Gantt charts at a time in the
widget, clicking an operation in one highlights that same operation in
the other as well.
In the panel, the Allocated Resource tab shows details on the
selected resource. Some are generic characteristics. Others depend on the operation
using the resource, and therefore change if you click another operation on that
resource. Available information includes:
- The work center, and the code and name of the resource.
- A check box indicating the resource allocation type for
the selected operation. If the operation is "forced" to use this resource
(check box selected), only an authorized user can choose a different
resource for the operation, typically in the scheduling app.
- The working mode of the resource: standard or batch,
for example.
- A check box indicating if this is a finite capacity resource. If it is not,
the plan considers that the resource has the capacity to handle any workload
it gets. Typically, in the data model, infinite capacity resources represent
subcontractors.
- The production rate of the resource for the selected operation. This is the
time it takes to produce a quantity of 1.
- The tooling used for the operation, if any, and whether there is time required for tool
changeover / setup before the operation can start. If there is a changeover
/ setup time, it is visible also on the graph. For more information, see
Symbols on Operations and Work Orders.
Note:
There can be tooling in the Code field, and
yet no changeover time. Typically, this happens when the current
operation and the previous operation on the resource require the same
tooling and setup. There is therefore no
need for a changeover between the two.
- The secondary resources used for the selected
operation, if any, with fields indicating how the operation contributes to
their workload. If the workload of a secondary resource is a time value, and
is always the same whatever the quantity of the operation, it appears in
Time constant. Similarly, if the workload is a
quantity that does not depend on the operation quantity, it appears in
Quantity constant. Conversely, if the workload of
the secondary resource varies with the operation quantity, the coefficient
to calculate it appears in Time coefficient or
Quantity coefficient respectively. If there is
also a constant value in that case, it means that the total workload of the
secondary resource is equal to the calculated value + the constant. Suppose
that to produce 1 part on the current resource, you need 2 hours of the
secondary resource, plus 1 hour of constant time. The quantity of the
operation is 10 parts. In that case, Time constant is
1 hour, and Time coefficient is 2 hours. The workload
of the secondary resource for that operation is: (Ten parts x 2 hours) + 1
hour = 21 hours.
Note:
If you are viewing the
Details panel from the Work Order Gantt
Chart, and the operation uses several resources, the
Allocated Resource tab details each of
them.
Clicking another operation updates the
Details panel accordingly. For more information, see
Gantt Chart Details Panel.
View Details on Operations
You can use the Details panel of the chart to view the
characteristics of operations.
-
On the Gantt chart, locate the operation on which you need further
information.
-
If the Details panel is open already, click the
operation. If the panel is not open, double-click the operation instead.
The panel displays information on the selected operation, including: Clicking another operation on the chart updates the
Details panel accordingly. For more information, see
Gantt Chart Details Panel.
|