Name
| If the context is a design project, a tree structure displays the root node of the product, expanded to the hazards, which can be further expanded to related hazards. If the context is a product, no root product object is shown since the context is already that of the product. Hazards are directly listed, which can be further expanded to related hazards. |
Type | The object type, which is "Hazard." |
State | The lifecycle state of the hazard object. |
Requirements | The number of requirements for the hazard. |
Title | The hazard title. |
Identification | Whether the hazard is "Known" or "Foreseeable." |
Condition | Whether the hazard is possible in a "Normal" or "Fault" condition. |
Major | The major classification of the hazard. |
Minor | The minor classification of the hazard. |
Sequence of Events | The sequence of events for hazardous situations. A rich-text enabled field. |
Hazardous Situation | Circumstances in which people, property or environment are exposed to hazards. |
Harm | Identifies physical injury or damage to people, damage to property or environment. |
Parent Hazards | The name of the parent hazards to which this hazard is associated as a related hazard. |
Analysis | An orange icon displays if this is the current process. Green indicates it is already completed. For information about the Analysis process, see Analysis. |
Evaluation | An orange icon displays if this is the current process. Green indicates it is already completed. For information about the Evaluation process, see Evaluation. |
Reduction | An orange icon displays if this is the current process. Green indicates it is already completed. For information about the Reduction process, see Reduction. |
Verification | An orange icon displays if this is the current process. Green indicates it is already completed. For information about the Verification process, see Verification. |
Completion | An orange icon displays if this is the current process. Green indicates it is already completed. For information about the Completion process, see Completion. |
Current Sev | Current severity of the hazard. |
Current Occ | Current occurrence of the hazard. |
Current RPN | Current Risk Priority Number for the hazard. The system calculates the RPN value by multiplying the occurrence (probability) value by the severity (impact) value. The occurrence and severity values can both range from 1 to 5, 1 being the lowest and 5 the highest. Therefore, the RPN can range from 1 (1x1) to 25 (5x5). |
Original Sev | Original severity of the hazard. |
Original Occ | Original occurrence of the hazard. |
Original RPN | Original Risk Priority Number for the hazard. The system calculates the RPN value by multiplying the occurrence (probability) value by the severity (impact) value. The occurrence and severity values can both range from 1 to 5, 1 being the lowest and 5 the highest. Therefore, the RPN can range from 1 (1x1) to 25 (5x5). |
Acceptable | Indicates whether the residual risk is acceptable. |
Benefit Exceeds Risk | Indicates whether the benefit exceeds the risk. |
Disclosure | The residual risk disclosure. |
Owner | The owner of the hazard. |