Monitor Resource Activity and Operation Execution
You can get a good grasp of the resource workload from the sequence of operations on
each resource. In addition, you can display the execution status of the operations. It
shows which operations are under way, and which operations are complete already, for
example.
-
From the Main View Settings section of the action bar (or Secondary View Settings, if the chart is in the
lower half of the widget window), click Work Order
Color.
-
From the list, select Operation Execution Status.
In the Gantt chart, operations change color to reflect the execution stage they are at.
By default, an operation is:
- Light gray (hex color: #e0e0e0) when the production plan has scheduled it,
but the operation has not reached production yet.
- Dark blue if it is ready for execution; hex color: #005686. The workshop /
teams know they can start working on the operation, but there is no further
information on execution.
- Light blue if it is in progress; hex color: #42a2da. The workshop / teams
have started performing the operation. Execution is under way.
- Green if it is complete; hex color: #57b847. The workshop / teams have
finished working on the operation. Execution is complete.
- Dark gray if the execution status of the operation is unknown; hex color:
#77797c. This is an anomaly. You may want to report it
to the persons in charge of the schedule, or of the manufacturing
execution system.
You can choose a different color scheme at any time. If you select
Advance / Delay, the colors reflect the advance /
delay of each operation with respect to its target end dateāor, missing
that, to its work order due date. This is another useful "status"
information on the operations in the plan. Whatever the color
scheme, specific hatch patterns always identify the operations that are in
progress or complete:
- Black and yellow hatches at the bottom of an operation indicate that the
operation execution is under way. The start date of the operation in the
plan is the date when execution began. The end date is the scheduled end
date.
- A white mesh pattern on an operation identifies the part of the operation
that is complete so far. This goes from the execution start date to the
current date.
- When execution is complete, the white mesh pattern covers the entire
operation bar. The hatches at the bottom disappear. The dates of the
operation in the plan are the start and end dates of its execution.
- In some cases, an operation can appear as both in progress (hatches) and
finished (white mesh on the whole bar). This happens when the app has not
received an execution end date for the operation yet, and the scheduled end
date is before the current date. Because the operation is entirely in the
past, the app considers that it is complete. Yet, until there is an
execution end date to confirm this information, the operation retains its in
progress status.
For clarifications on the current schedule, you can use the highlighting
feature described below to display the links between operations.
Monitor the Schedule of a Work Order on Resources
You can highlight all the operations of a specific work order and see the links between
them. This is useful to find out which resources these operations are using and how they
constrain one another. This can also clarify the reasons for idle times in the schedule
of resources.
-
From the
standard area
of the
action bar,
click
Highlight Work Order.
-
In the bar chart, click an operation of the work order to highlight.
The operation you clicked and those that belong to the same work order appear in color,
with their links. All other operations in the chart are gray. The links show the
order in which the highlighted operations take place, and the dependencies between
them. The links these operations have with operations of other work orders, if any,
appear as well. The colors of the links reflect their type:
- Light green is for total precedence links, that is: end-start
synchronization links with a minimum lead time (delay) between the two
operations.
- Dark green is for end-start synchronization links with
a maximum lead time (delay) between the two operations.
- Dotted lines are for links with errors. Their color reflects the type
of the original link. The operation that does not comply with the link
constraint shows a thick red top border. Its tooltip and the
Details panel show the error message.
The number of operations in the work order appears in the search result bar
at the bottom of the chart area. On using the filter feature of the search bar
to drill down the view, see Search and Filters on Gantt Charts.
Note:
If the chart previously highlighted 3DSearch results, it momentarily cancels them so they do not interfere
with the highlighted work order. Similarly, it hides dependency links between work orders. If you are displaying two
charts at a time in the widget, highlighting a work order in one chart
highlights it in the other as well.
To highlight a different work order, click an operation of that work order.
To highlight multiple work orders, Ctrl + click
operations. When you no longer need that feature, click a blank space to
cancel the current selection, and then from the action bar, click the feature icon to disable it. If the chart previously highlighted
3DSearch results, then it highlights them again. This is true also for
dependency links between work orders.
Monitor Alerts on Resources and Operations
The Resource Gantt Chart makes it easy to spot and analyze
any alerts on the current schedule of resources and operations.
-
In the data table of the chart, see if there are alert symbols.
Typically, there is an alert when the resource has changed from infinite to finite
capacity in the data model. All the operations planned beforehand on that
resource also raise an alert, because they need rescheduling.
-
On the graph area of the chart, see if there are operations with a thick
red top border.
This visual cue identifies the operations that have raised an alert,
either in relation to their resource or to some planning constraints. Their
tooltip and the Details panel of the chart show the
message of the alert.
Analyze each of the alerts to assess if the plan needs
correction, or remains valid as is. The most common alerts are as follows:
- Further to a change in the data model, a resource now has finite instead of infinite
capacity. The change has no impact on the operations that are already
complete or in progress on the resource, because their start and end dates
remain the same. Conversely, the change triggers an alert for the operations
that have not started yet, because their current sequence, which resulted
from an infinite capacity situation, is no longer valid. These operations
still appear on the resource in the Gantt chart, but from a planning
standpoint, they are now operations that need rescheduling.
- Further to a change in the data model, the current resource of an operation
is no longer a capable resource of that operation.
- The operation does not comply with the synchronization constraint it has
with another operation. This situation needs your attention, because it can
compromise the proper execution of the next steps of the production process.
View Details on Resources
You can use the Details panel of the chart to view the
characteristics of resources.
-
On the Resource Gantt Chart, locate the resource to
analyze.
-
If the Details panel is open already, click any
operation on that resource. If the panel is not open, you need to
double-click the operation instead.
Note:
If you are displaying two Gantt charts at a time in the
widget, clicking an operation in one highlights that same operation in
the other as well.
In the panel, the Allocated Resource tab shows details on the
selected resource. Some are generic characteristics. Others depend on the operation
using the resource, and therefore change if you click another operation on that
resource. Available information includes:
- The work center, and the code and name of the resource.
- A check box indicating if this is a finite capacity resource. If it is not,
the plan considers that the resource has the capacity to handle any workload
it gets. Typically, in the data model, infinite capacity resources represent
subcontractors.
- The production rate of the resource for the selected operation. This is the
time it takes to produce a quantity of 1.
- The tooling used for the operation, if any, and whether there is time required for tool
changeover / setup before the operation can start. If there is a changeover
/ setup time, it is visible also on the graph. For more information, see
Symbols on Operations and Work Orders.
Note:
There can be tooling in the Code field, and
yet no changeover time. Typically, this happens when the current
operation and the previous operation on the resource require the same
tooling . There is therefore no
need for a changeover between the two.
Clicking another operation updates the
Details panel accordingly. For more information, see
Gantt Chart Details Panel.
View Details on Operations
You can use the Details panel of the chart to view the
characteristics of operations.
-
On the Gantt chart, locate the operation on which you need further
information.
-
If the Details panel is open already, click the
operation. If the panel is not open, double-click the operation instead.
The panel displays information on the selected operation, including:
- Details on the work order the operation belongs to. For more information,
see View Details on Work Orders.
- The operation name.
- The operation quantity.
- The dates provided or calculated for the operation. The scheduled dates are the current
start and end dates of the operation in the plan. When the operation is
under way, its start date in the plan is the beginning of the remaining
activity. Execution dates are available only when the operation is under
way, or complete. They are the dates when the operation execution began and
finished. The target end date is the (optional)
objective for completing the operation. If the scheduled end date is
later than the target end date (or, missing that, later than the work
order due date), then the panel indicates that the operation is late.
Else, the app considers that the operation is on time.
- The maturity status of the operation: scheduled or in progress, for example.
- The execution priority of the operation. The higher the value, the higher
the priority.
- A check box indicating if the time it takes to perform the operation is proportional to
quantity or not.
- A check box indicating if it is possible to interrupt the operation. If it
is not, a typical implication is that the operation cannot start before a
nonworking day and finish after that day.
- Whether there is time required before or after the operation for actions that are
mandatory, but that do not use modeled equipment (time "out of machine").
For example: a drying time. If there is, this time is visible also on the
graph. For more information, see Symbols on Operations and Work Orders.
- Any alert in relation with the operation.
- Details on the resource the operation is using. For more information, see View Details on Resources.
Clicking another operation on the chart updates the
Details panel accordingly. For more information, see
Gantt Chart Details Panel.
|